Thermal Systems completed fabrication work for the 55 TPH Boiler project, delivering key structural components for efficient boiler performance. Our work included:

  • Ducting Fabrication: Manufactured boiler ducting as per approved drawings with precise alignment and material accuracy.
  • Economiser Casing: Fabricated the complete economiser casing structure following engineering and welding standards.
  • Quality Assurance: All work was executed under approved quality plans and safety guidelines, with final inspection before delivery.
  • On-Time Delivery: Both ducting and economiser casing were completed and handed over within the scheduled timeline.